Project introduction:
The customers are mainly engaged in the cold chain logistics business mode, and are engaged in the rental of cold storage. The cold storage has a construction area of 3000 square meters and a height of 6.5 meters. Temperature: - 18~- 25 ℃. The buffer zone is 5-10 ℃. PIR-150mm thick insulation board and XPS150mm thick ground are used. The refrigeration unit adopts Freon parallel screw unit and evaporative condenser.
The construction time of project reconstruction is 80 days. The following is the picture of on-site installation.